March: The slip-form works to the concrete shaft are
completed.
25 Apr.: The tube
and the lattice sections are raised to the upper part of the shaft.
7 June: The
platforms are lifted by two metres above construction level.
11 June: The final
lifting of the platforms starts.
14 June: The
platforms are lifted into their final position.
July: The platforms
are attached to the shaft. The final assembly of the exterior staircase begins.
Septem.: The
installation of G1 and G2 guys is completed and the provisional guys are dismantled.
3 Oct.:
Construction crane is dismantled.
25 Oct.: The upper
lattice section is hoisted into position.
31 Oct.: The
installation of G3 guys is completed.
4 Nov.: Lifting of
the upper tubular steel section begins.
19 Nov.: The upper
tubular steel section is lifted into its final position and the tower attains its final
height.
25 Dec.: The tower
is floodlit to coincide with Christmas
celebrations.
|